LOWERY LTD LONDON BRIDGE THAMESLINK PROJECT XMAS WORKS – 2020/2021

An immense volume of work was completed over the Xmas break by Lowery Ltd at London Bridge.

 

Main Stats:

Zero accidents or incidents recorded

113 separate Supervised shifts were carried to allow 8,170 working hours to be completed

CRMS upgrades carried out to existing Signalling, Telecoms and High Voltage routes on 21no separate Route Sections

Significant installation and modification to the CRMS on 16no separate Signalling Gantries

Extensive Signalling cable re-routing and diversions at 14no separate Signal locations

Multiple Civils defect clearance works were completed

All works utilised on and off track MEWPS & RRV’s throughout the duration of all the works programme

 

The Lowery team planned and professionally executed the Xmas works onsite to maximise the limited possession access available at one of the most congested locations on the Network Rail Route.

 

Well done to our multi disciplined teams who safely carried out these works during the Xmas break it is much appreciated by Lowery.

Many thanks also to the BAM Nuttall Thameslink Project Team & Network Rail for their ongoing support it is very much appreciated by the Lowery team.