24
Mar
2017
Week 50 – Sunningdale Stage 2

Week 50 – Sunningdale Stage 2

Successful completion of full SCADA pre-commissioning (end to end test) and new communication unit back to control room

24
Mar
2017
Week 51 Ash Vale

Week 51 Ash Vale

Successful Commissioning of 6 Track Isolation Switches including DC positive cabling at the Switchgear and Track end, Installation and commissioning of 4 advance plates and 16 DC negative cables, Section proving and Signal works testing

24
Mar
2017
Week 50 – Sunningdale Stage 1

Week 50 – Sunningdale Stage 1

Successful completion of cut and diversion of existing F2236 HV feeder, HV switchboard commissioned into service (bypass arrangement), commissioning of the new pilot cable (diversion)

24
Mar
2017
Week 49 – Emmbrook

Week 49 – Emmbrook

Successful completion of Installation and commissioning of 2 hot splice joints on the existing HV feeder F2239

24
Mar
2017
Week 44 – Whitmoor Stage 2 and 3

Week 44 – Whitmoor Stage 2 and 3

Lowery successfully completed full SCADA pre-commissioning (end to end test) and new communication unit back to control room, splitting existing feeder F2237 between Ascot and Bracknell to F2084 and F2085, Full RTU SCADA commissioning including all the alarms associated with the HV Switchgear and modules, HV protection (Line Differential Protection - Translay)

24
Mar
2017
Week 44 – Winnersh – installation of 2 advance pla

Week 44 – Winnersh – installation of 2 advance pla

Lowery complete the full pre-commissioning of HV module, TRU module and DC module including HV, LV and DC switchgear, Transformer Rectifier unit, SCADA RTU, Battery chargers, HV, LV and DC protection settings