Week 50 – Sunningdale Stage 2
Successful completion of full SCADA pre-commissioning (end to end test) and new communication unit back to control room
Week 51 Ash Vale
Successful Commissioning of 6 Track Isolation Switches including DC positive cabling at the Switchgear and Track end, Installation and commissioning of 4 advance plates and 16 DC negative cables, Section proving and Signal works testing
Week 50 – Sunningdale Stage 1
Successful completion of cut and diversion of existing F2236 HV feeder, HV switchboard commissioned into service (bypass arrangement), commissioning of the new pilot cable (diversion)
Week 49 – Emmbrook
Successful completion of Installation and commissioning of 2 hot splice joints on the existing HV feeder F2239
Week 44 – Whitmoor Stage 2 and 3
Lowery successfully completed full SCADA pre-commissioning (end to end test) and new communication unit back to control room, splitting existing feeder F2237 between Ascot and Bracknell to F2084 and F2085, Full RTU SCADA commissioning including all the alarms associated with the HV Switchgear and modules, HV protection (Line Differential Protection - Translay)
Week 44 – Winnersh – installation of 2 advance pla
Lowery complete the full pre-commissioning of HV module, TRU module and DC module including HV, LV and DC switchgear, Transformer Rectifier unit, SCADA RTU, Battery chargers, HV, LV and DC protection settings