30
Nov
2016
Staff Suggestion Scheme Bonus Award

Staff Suggestion Scheme Bonus Award

Congratulations go to Lowery Site Supervisor, Nigel Whisselle for earning £500 for his staff suggestion. His suggestion was the purchase of a pallet grab for the Lowery lorry mounted crane which would help prevent safety issues related to the slinging of loads and also to prevent damage to slinging equipment. This was viewed as a positive suggestion by the Company Directors which would assist in making the lifting of pallets of troughing safer.

24
Mar
2017
Week 51 Sunningdale - Stage 3 commissioning

Week 51 Sunningdale - Stage 3 commissioning

Successful completion. Works consisted of: o Split of the existing F2236 33kV feeder between Ascot and Knowle to F2082 and F2083 o Full RTU SCADA commissioning including all the alarms associated with the HV Switchgear and modules o HV protection (Line Differential Protection - Translay) o Commissioning of two new Auxiliary Transformers 33kV/415V

24
Mar
2017
Week 50 – Sunningdale Stage 2

Week 50 – Sunningdale Stage 2

Successful completion of full SCADA pre-commissioning (end to end test) and new communication unit back to control room

24
Mar
2017
Week 51 Ash Vale

Week 51 Ash Vale

Successful Commissioning of 6 Track Isolation Switches including DC positive cabling at the Switchgear and Track end, Installation and commissioning of 4 advance plates and 16 DC negative cables, Section proving and Signal works testing

24
Mar
2017
Week 50 – Sunningdale Stage 1

Week 50 – Sunningdale Stage 1

Successful completion of cut and diversion of existing F2236 HV feeder, HV switchboard commissioned into service (bypass arrangement), commissioning of the new pilot cable (diversion)

24
Mar
2017
Week 49 – Emmbrook

Week 49 – Emmbrook

Successful completion of Installation and commissioning of 2 hot splice joints on the existing HV feeder F2239